Installation
Video Tutorial
Before Installation
Prerequisites
- Ensure Thingsee Gateway is installed and operational (LED blinking green)
- Plan sensor locations considering all measurement types needed
- Prepare installation surface (clean and dry)
- Select appropriate mounting method for use case
Network Coverage Planning
- Maximum distance: 20m between sensors or to gateway
- Use intermediate sensors as routers for distances > 20m
- Account for signal attenuation from:
- Fire doors and thick walls
- Metal structures and equipment
- Dense building materials
Use Case Identification
Determine which sensors you’ll use:
- Temperature/Humidity - Climate monitoring
- Barometric Pressure - Weather tracking, floor detection
- Ambient Light - Occupancy inference, lighting status
- Accelerometer - Vibration/motion detection, position sensing
- Magnetic Switch - Door/window open/close status
This determines optimal placement and mounting method.
Placement Guidelines by Use Case
For Climate Monitoring (Temperature/Humidity)
Recommended Height
- Standard rooms: 1.5-1.8m from floor (breathing height)
- Large spaces: Multiple sensors at consistent height
- Cold storage: Lower placement acceptable (monitor product level)
Good Placement
✅ Representative of room conditions
✅ Central location or along walls
✅ Away from direct airflow
✅ Accessible for battery replacement
Avoid
❌ Direct sunlight or near windows
❌ Near heating/cooling sources or vents
❌ Corners (poor air circulation)
❌ Behind doors or furniture
For Light Sensing (Ambient Light)
Sensor Orientation
- Sensor face should point toward general room lighting
- Not obstructed by furniture or equipment
- Consider multiple light sources
Good Placement
✅ Central ceiling mount (facing down)
✅ Wall mount facing room interior
✅ Position with clear view of lights
Avoid
❌ In shadows or under overhangs
❌ Facing windows (sun overwhelms room lights)
❌ Behind obstacles
❌ In cabinets or enclosed spaces
Note: Light measurement is indicative (not calibrated). Suitable for on/off detection and relative changes, not absolute lux measurement.
For Door/Window Monitoring (Magnetic Switch)
Installation Configuration
Sensor and magnet must be aligned when door/window is closed.
Recommended spacing: 5-15mm gap between sensor and magnet
Door Frame Installation
- Sensor location: On door frame (stationary)
- Magnet location: On door (moving part)
- Alignment: Sensor and magnet parallel, facing each other
- Test: Close door, verify alignment before final mounting
Window Installation
- Sensor: On window frame
- Magnet: On sliding/opening window panel
- Check alignment when window closed
Magnet Types
- Included magnet: Small rectangular magnet (usually provided)
- Alternative: Any strong permanent magnet (neodymium recommended)
- Orientation: North/south pole facing sensor (test orientation for best detection)
For Machine Usage Monitoring (Accelerometer)
Mounting Requirements
Critical: Sensor must be mechanically coupled to equipment for vibration detection
Good Practice
✅ Directly on vibrating surface
✅ Rigid mounting (screw preferred over tape)
✅ Flat, clean mounting surface
✅ Consistent sensor orientation
✅ Test detection before finalizing installation
Avoid
❌ Flexible or dampened mounting
❌ Tape mounting on rough surfaces (use screws)
❌ Indirect coupling (e.g., on nearby shelf)
❌ Loose or wobbling mount
Orientation Considerations
- X, Y, Z axes report separately
- Consistent orientation across similar equipment
- Document orientation for data interpretation
- Most sensitive to vibration perpendicular to mounting surface
Vibration Range Selection
- Machine Usage Mode: 0-8G (typical machinery)
- High Movement Mode: 0-16G (heavy machinery, impact loads)
- Contact Haltian support to configure mode
For Position/Orientation Detection (Accelerometer)
Use Case Examples
- Detect if cabinet door opened (orientation change)
- Monitor if equipment moved or tilted
- Track asset position (vertical vs. horizontal)
Installation Tips
- Note initial orientation (X, Y, Z gravity values)
- Secure mounting to asset being monitored
- Document expected orientations for different states
Mounting Methods
Thingsee ENVIRONMENT supports three mounting methods:
Method 1: Adhesive Tape Mounting
Best for:
- Smooth, non-porous surfaces (painted walls, tiles, glass, metal)
- Temporary installations or pilot projects
- Climate monitoring applications
- Locations where drilling not permitted
Not suitable for:
- Rough or textured surfaces
- High-vibration applications (use screws)
- Outdoor or high-humidity environments
Materials Needed
- Double-sided adhesive tape (foam tape recommended)
- IPA solvent (isopropyl alcohol)
- Clean cloth
Installation Steps
Clean the surface:
- Wipe with IPA solvent
- Allow to dry completely (1-2 minutes)
- Ensure no dust, grease, or residue
Prepare the sensor:
- Open sensor with provided opening key
- Clean sensor back surface (if needed)
- Locate mounting area on sensor back
Apply tape:
- Cut tape to match sensor footprint
- Press tape firmly on sensor back for 5 seconds
- Remove tape backing paper
Mount the sensor:
- Position at desired location
- Press firmly against surface for 10 seconds
- Hold steady to ensure adhesion
Wait before loading:
- Allow 15 minutes for adhesive to set
- Do not disturb during this period
- Then proceed with battery installation
Method 2: Screw Mounting
Best for:
- Permanent installations
- Vibration monitoring applications (Machine Usage Mode)
- Rough or textured surfaces
- High-reliability requirements
Required for:
- Machine usage monitoring (vibration detection)
- High-vibration environments
Materials Needed
- 2x screws (size: 2-3mm diameter, length based on wall type)
- Screwdriver
- Wall anchors (for drywall or concrete)
- Drill (if using anchors)
- Pencil for marking
Installation Steps
Mark screw positions:
- Hold sensor at desired location
- Mark screw hole positions with pencil
- Verify height and alignment
Prepare the wall (if needed):
- For concrete: Drill pilot holes, insert anchors
- For drywall: Insert appropriate wall anchors
- For wood: No anchor needed (pilot hole recommended)
Mount the sensor:
- Align sensor screw holes with wall holes/anchors
- Insert screws through sensor mounting holes
- Tighten securely but do not over-tighten
- Verify sensor is level and flush with surface
Check stability:
- Gently pull on sensor to verify secure mounting
- No wobbling or movement
- For vibration monitoring: Ensure very rigid connection
Method 3: Magnetic Mounting
Best for:
- Temporary monitoring or testing
- Metal surfaces (equipment housings, cabinets, doors)
- Repositionable installations
- Quick deployment scenarios
Requirements:
- Metal surface (ferromagnetic: steel, iron)
- Magnetic mounting accessory (contact Haltian for availability)
Installation Steps
Prepare surface:
- Clean metal surface (remove dirt, grease)
- Ensure flat, smooth area for magnet contact
Attach magnet to sensor:
- Secure magnetic mount to sensor
- Verify solid attachment
Position on surface:
- Place sensor on metal surface
- Magnet should hold firmly
- Test: Gently pull to ensure secure attachment
Verify stability:
- Should not slide or fall when touched
- If loose, relocate to better surface area
- Not suitable for high-vibration monitoring
Note: Magnetic mounting may interfere with magnetic switch sensor if used for door/window monitoring. Use screw or tape mounting for magnetic switch applications.
Battery Installation
Battery Specifications
- Type: 2x AAA alkaline batteries
- Recommended: Varta Industrial Pro 1.5V AAA LR03
- Alternatives: High-quality alkaline AAA batteries (Duracell, Energizer)
- NOT compatible: Lithium, rechargeable NiMH (voltage mismatch)
Installation Steps
For New Installation (Before Mounting)
Open the sensor:
- Hold sensor in hand
- Insert opening key in side hole
- Twist to separate A-cover from B-cover
Install batteries:
- Insert batteries into A-cover battery compartment
- Observe correct polarity (+ and - markings inside)
- Ensure both batteries fully seated
Verify operation:
- LED will flash briefly to indicate power-on
- Sensor begins initialization sequence
Close the sensor:
- Align A-cover with B-cover (Thingsee logo upright)
- Press covers together until they click securely
- Verify no gaps between covers
For Wall-Mounted Sensor (Battery Replacement)
Open while mounted:
- Insert opening key in side hole (sensor remains on wall)
- Twist to release A-cover
- Pull A-cover away from B-cover
Remove old batteries:
- Note battery orientation before removal
- Remove both batteries
- Dispose of properly (battery recycling)
Install new batteries:
- Insert fresh AAA batteries
- Match polarity markings
- Ensure full contact
Reattach A-cover:
- Align covers carefully
- Press together until secure click
- Verify Thingsee logo orientation (upright)
Specialized Installation Configurations
Door/Window Monitoring Setup
Complete Installation
Install sensor on door frame (stationary part):
- Use screw mounting for permanent installation
- Tape mounting acceptable for temporary setups
- Position so sensor face can align with magnet
Install magnet on door (moving part):
- Adhesive-backed magnet typically provided
- Position to align with sensor when door closed
- Verify 5-15mm gap when closed
Test alignment:
- Close door/window
- Magnet and sensor should be parallel, facing each other
- Open and close several times
- Verify IoT Studio shows state changes
Fine-tune positioning:
- Adjust magnet position if needed
- Optimal gap: 5-15mm
- Test detection reliability
Machine Usage Monitoring Setup
Critical Installation Steps
Select mounting location:
- Flat surface on equipment housing
- Position that receives vibration clearly
- Avoid dampened or isolated spots
Use screw mounting (required):
- Tape mounting insufficient for vibration detection
- Rigid mechanical coupling essential
- 2-screw mounting recommended
Verify orientation:
- Document X, Y, Z axis orientation
- Consistent across multiple machines
- Aids in data interpretation
Enable Machine Usage Mode:
- Contact support@haltian.com
- Provide sensor ID
- Specify vibration range needed (8G or 16G)
- Support will configure remotely
Test detection:
- Run equipment through normal cycle
- Verify vibration detection in IoT Studio
- Adjust sensitivity if needed (contact support)
Post-Installation Verification
Network Connection
Wait for network join:
- Device automatically joins Wirepas mesh network
- Typical join time: 1-5 minutes
- May take up to 10 minutes in busy networks
Verify in Haltian IoT Studio:
- Log into IoT Studio portal
- Navigate to device list
- Confirm sensor appears with correct ID
- Check “Last Seen” timestamp (should be recent)
Initial Data Collection
First readings:
- Temperature, humidity, pressure, light available immediately
- Accelerometer provides orientation data
- Magnetic switch shows current state
- Expect first readings within 5-10 minutes
Baseline establishment:
- Monitor readings during first 24 hours
- Verify measurements reasonable for environment
- Check all enabled sensors reporting
Signal Strength Check
Review RSSI values in IoT Studio:
- Good signal: > -70 dBm
- Acceptable: -70 to -85 dBm
- Poor: < -85 dBm
If signal is poor:
- Add intermediate sensor as router
- Reposition sensor closer to gateway
- Check for physical obstructions or RF interference
Functional Testing
For Climate Monitoring
- Verify temperature reads room temperature
- Check humidity within expected range
- Pressure should be ~1013 hPa at sea level (adjust for altitude)
For Light Sensing
- Turn lights on/off, verify lux changes
- Should see significant difference (thousands of lux)
For Magnetic Switch
- Open/close door/window
- Verify state changes appear in IoT Studio within minutes
- Counter should increment with each state change
For Machine Usage
- Run equipment through normal operation
- Verify vibration detected in IoT Studio
- Check X, Y, Z axis values change during operation
Installation Checklist
- Gateway operational and connected
- Installation location planned (use case considered)
- Surface cleaned and prepared
- Sensor unpacked and identified (QR code noted)
- Mounting method selected (tape/screw/magnet)
- Sensor securely mounted (or batteries installed if mounting first)
- Batteries installed correctly (polarity matched)
- Covers attached securely (logo upright)
- Device appears in IoT Studio
- Initial readings received (all active sensors)
- Signal strength acceptable (RSSI > -85 dBm)
- Magnetic switch tested (if applicable)
- Vibration detection verified (if Machine Usage Mode)
- Documentation updated (location, sensor ID, orientation)
Support
For installation assistance:
- Email: support@haltian.com
- Documentation: Review How-To Guides
- Machine Usage Mode: Contact support to enable
- Technical Support: Site-specific installation questions